The cascade scheme of neutralization of phosphoric acid ammonia has been replaced

The cascade scheme of neutralization of phosphoric acid ammonia consisting of 3 collections D =3m, N =2m has been replaced with one device "SAI-100" - the high-speed shock-absorber - the evaporator - the sizes D =1m, by N =3m in which at the same time there were reactions of neutralization and evaporation, to formation of an ammofosny pulp. Installation of bubbling type for evaporation of an ammofosny pulp is included in engineering procedure that has allowed to increase performance of devices BGS sharply.

17 February 2009

It is transformed into Joint-stock Company Ammofos-Maxam

Based on the 1st queue of JSC Ammofos new technologies and the equipment for receipt of the granulated ammophos have been created. So, the technological chain the "dryer granulator" consisting of a drying tower, a smachivatel and a drum of the granulator has been replaced with one device "BGS" (a drum the granulator - the dryer), with release production the areas: the technological thread became more compact in hardware execution.

9 February 2009

The Ammofos production association transformed to Ammofos open joint stock company

11 December 2001

The shop on production of environmentally friendly fiber boards is put into operation

Capacity of shop - 500 thousand sq.m. All processing equipment is grouped in the form of one processing line. Drevesno - fibrous plates are made on the basis of a guzapaa - stalks of a cotton and a kenaf.

25 October 1993

Almalyk chemical plant is transformed to the Almalyk production association "Ammofos"

14 February 1992

The shop on release of extraction phosphoric acid No. 4 is constructed and put into operation

Production capacity on release of sulfuric acid makes 500 thousand tons of MNG a year. Experiment on designing, construction and operation of the Almalyk chemical plant has formed the basis of designing of a number of the entities in Central Asia of production of the granulated nitrogen-phosphorus fertilizers based on poor ores of the basin of Karatau.

3 November 1986

The shop on release of sulfuric acid (SK-40) is put into operation

16 September 1981

Reconstruction of the second queue of the entity is performed

During reconstruction of the second queueof production, considering operating experience of the 1st queue, in addition to the 4th BGS existing on the project L=16m have been established 2 more BGS in size D =4,5m. Functioning of the equipment is ensured by SAI-150. Reconstruction has allowed to increase capacity on phosphoric fertilizers of shop of ammophos - 2 to 207,2 thousand tons of 100% of P2O5 a year. The EFK-2 shop has been added with one more rotary K-100 vacuum filter that has allowed to increase capacity of shop on release of phosphoric acid to 136,4 thousand tons of 100% of P2O5 a year.

13 August 1980

The third queue is put into operation

Developers of new devices and technologies were specialists of the entity and staff of institutes of NIUIF and NIIHIMMASh. A general designer of all 3 queues of the entity was URALGIPROKHIM.

10 May 1978

The second queue is put into operation

4 April 1973

The first stage of production on release of extraction phosphoric acid

The first stage of production on release of extraction phosphoric acid and ammophos has become operational. Release of the granulated ammophos from the phosphorites of Karatau containing 24,5% of phosphoric anhydride (P2O5) is mastered.

18 December 1969

Process of receipt of the granulated ammophos on a basis of phosphorites Karatau (Kazakhstan) has been performed

By staff of the entity together with research and design and institutes for the first time in world practice of the tukovy industry, the technology of direct extraction of phosphoric acid from poor phosphorites of Karatau is developed. The plant is constructed on the project the Urals by GIPROHIMA, based on data NIUIF.